If your group owns land in Malaysia and intends to build and sell more than four homes on it, you are not a landowner with a construction budget — you are a housing developer, and you cannot legally advertise, take a booking fee or sign a sale and purchase agreement until the National Housing Department has issued you a Developer's Licence and, separately, an Advertising and Sale Permit for that specific development. The gate is set by the Housing Development (Control and Licensing) Act 1966 — Act 118 — and it is unusually unforgiving: a company with less than RM250,000 of paid-up cash capital is rejected outright, the deposit is 3% of your estimated construction cost, and the sale contract is not yours to draft. 2026 is also the year the whole statute is being replaced. This is the map.

1. Why 2026 is the wrong year to assume the rules are settled
Three things are moving at once, and a foreign investor reading a 2023 guide will get all three wrong.
First, the enforcement environment has hardened. KPKT's own figures put 303 private housing projects in Peninsular Malaysia in "sick" status as at 30 June 2026, covering 43,288 units and RM40.25 billion of gross development value, of which 100 projects are confirmed abandoned, affecting 27,998 units and 14,961 buyers. Selangor alone accounts for 41 of the abandoned projects. Against that, the ministry's special task force reports 1,647 projects revived since 2023. The Madani Housing Reform, in force from 1 January 2026, sets a target of zero new abandoned projects by 2030. Every tightening you meet at the licensing counter traces back to those numbers.
Second, Act 118 itself is on its way out. The minister has confirmed that a new Real Property Development Act (Akta Pemajuan Harta Tanah, "RPDA") is being drafted to replace Act 118 and is expected to be tabled in Parliament during a 2026 sitting. The most consequential design change announced so far: the RPDA is intended to cover commercial developments, not just housing. If your Malaysian project is a serviced-apartment or SOHO scheme on a commercial title, you are currently outside the Act 118 regime — and that is precisely the gap the RPDA is meant to close.
Third, the Urban Renewal Bill — the law that was going to govern redevelopment of ageing strata blocks, and which a great deal of foreign capital was waiting on — was withdrawn by the Cabinet on 23 January 2026 to be refined and re-tabled later. It had reached first reading in August 2025 with a standardised 80% consent threshold. There is at present no urban renewal statute in force. Treat any pitch built on "the URA will let us assemble that site" as a plan without a legal basis until the bill is passed.
2. What actually triggers the licence — the "more than four units" test
Act 118 is not a general property law. It bites on a defined activity: developing or constructing more than four units of housing accommodation, or laying out land into more than four lots for the purpose of building housing accommodation. Cross that line and you are a "housing developer" and need a licence under section 5. Stay at four units or fewer and you are outside the Act — which is why the HIMS application form rejects a land section containing fewer than five individual titles.
Three boundaries matter more than foreign investors expect:
| Situation | Position |
|---|---|
| More than 4 units of housing accommodation, Peninsular Malaysia | Act 118 applies in full — licence, permit, HDA account, statutory contract |
| Same project in Sabah | Governed by the Housing Development (Control and Licensing) Enactment 1978, administered by the state ministry — not by JPN in Putrajaya |
| Same project in Sarawak | Governed by the Housing Developers (Control and Licensing) Ordinance 2013 — again a separate state regime |
| Serviced apartments / SOHO on commercial title | Generally outside Act 118 today. No HDA account, no Schedule H, no statutory LAD. The proposed RPDA is intended to bring these in |
| Purely commercial development (shoplots, offices, industrial) | Outside Act 118 today; local authority and planning approvals still apply |
| Four units or fewer | Outside Act 118; ordinary contract law and planning approvals apply |
The Sabah and Sarawak point is the one that catches groups who assume a Malaysian federal licence travels. It does not — in the same way that an employment pass issued in Peninsular Malaysia does not entitle your staff to work in Sarawak.
3. Can a foreign-owned company hold the licence?
Yes — with three qualifications that decide the structure.
The licensee must be a Malaysian-incorporated entity. The licence is granted to a company, and the HIMS application pulls company particulars directly from SSM. In practice that means a Sdn. Bhd., either wholly foreign-owned or a joint venture with a local landowner. If your SSM record is wrong, fix it at SSM before you apply — HIMS will not let you edit it in the application. Our step-by-step incorporation guide covers the entity itself.
The land, not the company, is where foreign status bites. A company with more than 50% foreign shareholding is a "foreign company" for land purposes, and its acquisition of land requires the written consent of the State Authority under section 433B of the National Land Code. Separately, the national Guideline on the Acquisition of Properties (in force since 13 July 2022) requires approval where an acquisition dilutes Bumiputera or government interest in property valued at RM20 million and above. State consent is not a formality: it is where conditions — including Bumiputera equity or unit conditions — are commonly attached.
Your buyers face price floors you do not control. Foreign purchasers of residential property must meet state minimum-price thresholds, and these are set by each state, not by Putrajaya. As at 2026 the picture ranges roughly from RM500,000 for strata on Penang mainland to RM3,000,000 for landed property on Penang island, with Selangor at RM2,000,000 in Zones 1 and 2 and RM1,000,000 in Zone 3, and Johor at RM1,000,000 for strata. If your commercial model assumes you will sell most units to buyers from your home market, model those floors before you buy the land — they can remove your entire target segment from a project priced for the local mass market. Some relief exists through MM2H participation and inside designated zones.

4. The Developer's Licence: capital, credit and the RM250,000 wall
Applications are made only through the Housing Integrated Management System (HIMS) at hims.kpkt.gov.my, which has been the sole channel since 31 January 2022. Manual or hardcopy submissions are not accepted. The single most important change of that date: a developer now holds one Developer's Licence for all its developments, instead of one licence per project.
| Item | Requirement |
|---|---|
| Paid-up cash capital | RM250,000 minimum. Applications below this are rejected — paragraph 6(1)(a), Act 118. It must be paid up in cash, not by capitalising a director's advance on paper |
| Financial statements | Audited annual accounts for the latest one or two years. A newly incorporated company uploads a letter on its letterhead explaining that no audited accounts exist yet, together with its SSM registration certificate |
| Credit report | A company credit report (CTOS or Experian) dated no more than three months before submission |
| Statutory declaration | Form L2C, sworn before a Commissioner for Oaths, valid if sworn within six months of the application |
| Land | At least five individual titles must be entered where individual titles exist. If the developer is not the registered proprietor, the full stamped joint-venture agreement — containing an express Act 118 and 1989 Regulations compliance clause, signed by both parties, witnessed by a solicitor and sealed — must be uploaded |
| Processing time | 60 working days from a complete application to "Awaiting Payment" status |
| Fee | RM5,000 for a five-year licence, plus a RM50 processing fee, payable online within 30 days of approval or the application lapses |
| Query window | A query ("Kuiri Semakan") auto-terminates the application if the developer does not respond within 14 days |
| Discretion | The Controller may grant, refuse, or attach conditions, and may vary or cancel conditions at any time under section 14 and subsection 5(5) of Act 118 |
Two of these routinely sink first-time applications by foreign groups. The first is the land ownership chain: if the developer company is not yet registered on the title, JPN wants either the completed transfer or at least a stamped Form 14A showing the transfer is in progress at the Land Office — otherwise the application is rejected outright. The second is the joint-venture agreement. A commercially competent JV drafted offshore, without the Act 118 compliance clause, without a solicitor's attestation and without stamp duty paid, will be bounced. Have the JV drafted for the licence application, not only for the deal.
5. The Advertising and Sale Permit — one per development, per phase
The licence lets you exist as a developer. The Advertising and Sale Permit (Permit Iklan dan Jualan, "AP") lets you sell one specific development. Regulation 5 of the 1989 Regulations makes it an offence to advertise or sell without it, and "advertise" is read broadly — a show unit, a WeChat post, a brochure or a price list all count.
| Item | Position |
|---|---|
| Scope | Issued for one development or one phase. Applications combining phases or splitting a phase are not accepted |
| Prerequisite | A valid, unexpired Developer's Licence covering that land. If land particulars changed, the licence must be amended first |
| Processing time | 40 working days from a complete application to "Conditional Approval" |
| Fee | RM500 per year or part of a year — regulation 5(7) |
| After conditional approval | The financial section must be completed and submitted within 30 days, evidencing the HDA account and the deposit |
| Cost disclosure | Construction, consultant, financing, overhead, marketing and land costs must all be declared, with construction and consultant costs certified by the project architect and GDV reconciled to the price schedule |
| Bumiputera units | Units reserved as Bumiputera lots by the State Authority must be flagged in the unit schedule; landowner units under a JV are printed on the permit as not for sale |
| Sale model | Declared as sell-then-build (JKB) or build-then-sell 10/90 (BKJ 10/90) — this determines which statutory contract schedule applies |
6. The Housing Development Account and the 3% deposit
This is the part foreign finance directors misread most often, because it has no analogue in most home markets.
Under section 7A of Act 118 and the Housing Developers (Housing Development Account) Regulations 1991, a licensed developer must open and maintain a Housing Development Account (HDA) with a bank for each development, and all money received in respect of that development — every progress payment from every buyer and their financiers — must be paid into it. Withdrawals are restricted to prescribed development purposes. This is a statutory ring-fence, not a management convention: money in an HDA is not group cash and cannot be swept upstream to a parent, lent to an affiliate, or used to fund the next site.
The deposit sits alongside it. The original flat RM200,000 deposit was replaced by 3% of the estimated cost of construction — construction, consultant, financing and overhead costs necessary to complete the development, excluding land cost. The developer satisfies it in one of three ways, evidenced in the AP application:
- Cash deposited into the HDA account (Appendix A1 confirmation);
- Bank guarantee, issued in JPN's prescribed format and split into an 80% and a 20% guarantee (Appendix A2); or
- A trust account arrangement.
A reduction or exemption of the 3% deposit can be approved by the Controller, and HIMS has a field for it — but treat it as an application, not an expectation. In cash-flow modelling, budget the deposit as locked capital from before your first sale until the Controller releases it, and budget the HDA as a set of accounts you do not control. For a RM100 million construction cost, the deposit alone is RM3 million.

7. The sale contract you do not get to draft
Once you hold a licence and a permit, the terms of sale are largely prescribed. The 1989 Regulations attach statutory contract forms, and departing from them is not a commercial negotiation — it is unenforceable.
| Schedule | Applies to | Delivery of vacant possession |
|---|---|---|
| Schedule G | Landed housing, sell-then-build, individual title | 24 months from the date of the agreement |
| Schedule H | Strata (subdivided building), sell-then-build, master title | 36 months from the date of the agreement |
| Schedule I | Landed housing, build-then-sell 10/90 | Per the schedule terms |
| Schedule J | Strata, build-then-sell 10/90 | Per the schedule terms |
Three consequences follow:
Late delivery is priced for you. Liquidated ascertained damages run at 10% per annum on the purchase price, calculated daily from the day after the delivery date until vacant possession is actually delivered. On a RM600,000 unit, that is roughly RM164 a day, per unit. On a 300-unit block delivered six months late, it is a nine-figure conversation.
The defect liability period is 24 months from delivery of vacant possession, during which the developer must make good defects notified by the buyer, at its cost.
Disputes are cheap for the buyer. The Tribunal for Homebuyer Claims hears claims up to RM50,000, with no requirement for the buyer to be legally represented. A developer facing several hundred small tribunal claims cannot defend them the way it would defend one High Court action — which is exactly the design intent. Larger commercial disputes still go the conventional route described in our guide to enforcing a Malaysian contract.
Note also that the developer may not collect a booking fee or any payment before the statutory agreement is signed. Taking "expression of interest" money at a soft launch, a common practice in other markets, is an offence here.
8. The correct sequence — and where the time actually goes
The single most expensive mistake is running these steps in the wrong order, because several of them are conditions precedent to the next.
| Step | Authority | Indicative time |
|---|---|---|
| Incorporate the Sdn. Bhd.; capitalise to at least RM250,000 in cash | SSM | 1–2 weeks; capital timed before licensing |
| Acquire the land or sign the JV; obtain state consent under s.433B if foreign-controlled | State Authority / Land Office | 2–8 months, state-dependent |
| Convert land use to "housing" or surrender-and-realienate (SBKS); pay the premium in full | Land Office | 3–12 months |
| Planning permission, building plan approval, earthworks | Local authority (PBT) | 3–9 months |
| Apply for the Developer's Licence in HIMS | JPN, KPKT | 60 working days to payment stage |
| Apply for the Advertising and Sale Permit | JPN, KPKT | 40 working days to conditional approval |
| Open the HDA account; place the 3% deposit; complete the AP financial section | Bank / JPN | 30 days from conditional approval |
| Launch, advertise, sign Schedule G/H agreements | — | Clock starts: 24 or 36 months to vacant possession |
Realistically, a foreign group starting from a clean sheet — new company, land to acquire, land use to convert — should plan on 12 to 24 months before it can legally advertise a single unit. The licence and permit are, at 100 working days combined, among the shorter items on that list. The land conversion and the premium are usually the long pole.

9. Eight traps that cost foreign developers money in Malaysia
Treating paid-up capital as a formality. RM250,000 must be paid up in cash and visible in the SSM record. A company registered with RM1 in share capital, funded entirely by director's advances, fails paragraph 6(1)(a) on day one and cannot be fixed the week before submission.
Signing the JV before the licence is scoped. A JV that lacks the Act 118 compliance clause, is unstamped, or is signed without solicitor attestation and company seal, will not support a licence application — regardless of how well it works commercially.
Advertising before the permit. A pre-launch WeChat campaign or an overseas roadshow selling Malaysian units without an AP is an offence under the 1989 Regulations, and it is exactly the kind of activity that surfaces later in an enforcement file.
Assuming a commercial-title serviced apartment carries no obligations. Today it sits outside Act 118 — but it also means your buyers have no statutory LAD, no HDA protection and no tribunal, which is increasingly a marketing liability, and the RPDA is expected to close the gap.
Modelling the 3% deposit as an expense. It is locked capital, not a cost, and it is on top of the equity your construction programme needs.
Sweeping HDA cash. Progress payments in the HDA cannot be moved upstream to fund another project or repatriated as though they were profit. Distributions come later, and through the route described in our guide to getting money out of Malaysia.
Ignoring the buyer-side price floors and the Bumiputera quota. The state's minimum foreign purchase price and its Bumiputera unit quota and discount both change your achievable average selling price. They belong in the feasibility study, not in the launch meeting.
Forgetting that development profit is income, not a capital gain. Land held as trading stock by a developer produces business income taxed at corporate rates, not real property gains tax. Groups that structure for RPGT and discover they are on the income tax side of the line usually find it out too late to change it.
10. What to do next
If you are evaluating a Malaysian residential project, the order of work is: confirm which state regime applies; confirm whether the scheme is inside or outside Act 118; check the state's foreign purchase floor against your intended buyer profile; then capitalise the Sdn. Bhd. properly before anything else, because RM250,000 in paid-up cash capital is the one requirement with no discretion attached to it.
ONEKEY BIZ handles the corporate and licensing side of that sequence end to end for foreign-owned groups — incorporation and capitalisation, the SSM record that HIMS reads, the joint-venture documentation the Controller will accept, the HIMS licence and permit submissions, and the accounting discipline that a Housing Development Account demands. Talk to us through our legal and regulatory advisory service, or contact our consultants in Mandarin or English for a fixed-fee scope on your specific site.
Frequently asked questions
Can a foreign-owned company hold a housing developer licence in Malaysia?
Yes. The licence is granted to a Malaysian-incorporated company, so a wholly foreign-owned Sdn. Bhd. or a joint venture with a local landowner can hold it, provided it has at least RM250,000 of paid-up cash capital as required by paragraph 6(1)(a) of Act 118. Foreign status bites at the land rather than the licence: a company with more than 50% foreign shareholding needs the State Authority's written consent under section 433B of the National Land Code to acquire the land, and approval under the national Guideline on the Acquisition of Properties is required where an acquisition dilutes Bumiputera or government interest in property valued at RM20 million and above.
How much does a Malaysian developer's licence cost and how long does it take?
The licence fee is RM5,000 for a five-year licence plus a RM50 processing fee, payable online within 30 days of approval or the application lapses. The National Housing Department's published processing time is 60 working days from a complete application to "Awaiting Payment" status. The separate Advertising and Sale Permit takes 40 working days to conditional approval and costs RM500 per year or part of a year. Both are submitted only through the Housing Integrated Management System (HIMS); manual submissions are not accepted.
What is the 3% deposit and the Housing Development Account?
Section 7A of Act 118 and the Housing Developers (Housing Development Account) Regulations 1991 require a licensed developer to open a Housing Development Account for each development and pay all money received for that development into it, with withdrawals limited to prescribed development purposes. The licensing deposit, formerly a flat RM200,000, is now 3% of the estimated cost of construction — construction, consultant, financing and overhead costs, excluding land — and may be satisfied in cash into the HDA, by a bank guarantee issued in the department's prescribed format and split 80% and 20%, or through a trust account. A reduction or exemption may be approved by the Controller but should not be assumed.
Do serviced apartments and SOHO units on commercial title fall under Act 118?
Generally not, as the Act applies to housing accommodation. A scheme on commercial title therefore sits outside the licensing regime today, which also means its buyers have no Housing Development Account protection, no statutory 10% per annum liquidated ascertained damages for late delivery and no access to the Tribunal for Homebuyer Claims. This is one of the gaps the proposed Real Property Development Act (RPDA), which the minister has said will cover commercial developments and is expected to be tabled during a 2026 parliamentary sitting, is intended to close.
Is the Urban Renewal Act in force in Malaysia?
No. The Urban Renewal Bill reached first reading in the Dewan Rakyat in August 2025 with a standardised 80% consent threshold for redevelopment, but the Cabinet decided on 23 January 2026 to withdraw it for further refinement and re-tabling at a later date. There is currently no urban renewal statute in force, so any redevelopment strategy that depends on it has no legal basis yet.
Related services
We handle the process described in this article end-to-end.
- Legal ConsultationMalaysia commercial law advisory covering corporate, contract and cross-border matters.
- Contract DraftingProfessional drafting of Malaysia-compliant commercial contracts in English & Chinese.
- Sdn. Bhd. IncorporationRegister a private limited company (Sdn. Bhd.) with SSM end-to-end.
Sources & references
- Jabatan Perumahan Negara, KPKT — Lesen Pemaju Perumahan (Seksyen 5, Akta 118)
- KPKT TEDUH — Garis Panduan Permohonan Lesen Pemaju Perumahan (Lesen Pemaju Baharu)
- KPKT TEDUH — Garis Panduan Permohonan Permit Iklan Dan Jualan (Permit Baharu)
- Housing Integrated Management System (HIMS), KPKT
- Laws of Malaysia — Housing Development (Control and Licensing) Act 1966 (Act 118)
This article is general information only, not legal, tax or immigration advice. Policies, thresholds and official fees are set by the relevant Malaysian authorities and may change. Talk to our consultants about your specific situation.